
Subject
title
Award and Authorize the City Manager to Execute a Contract Responsive to Invitation for Bids (IFB) #25-25, Croydon Creek & Calvin Park Tributary Stream Restoration Project, to Kinsley Construction, LLC, of York, PA in the amount not to exceed $4,640,979.75
end

Department
PW - Engineering

Recommendation
Staff recommends that the Mayor and Council award and authorize the City Manager to Execute a Contract Responsive to Invitation for Bid (IFB) #25-25, Croydon Creek & Calvin Park Tributary Stream Restoration Project, to Kinsley Construction, LLC, of York, PA in the amount not to exceed $4,640,979.75.
Discussion
IFB #25-25, Croydon Creek & Calvin Park Tributary Stream Restoration, is a publicly bid, stream restoration project, within Civic Center Park, near the Croydon Creek Nature Center of Rockville, MD. This project restores the streams at Croydon Creek and the Calvin Park Tributary to Rock Creek. These streams have highly eroded stream banks that are significant sources of sediment that reduce water quality within the watershed and ultimately the Chesapeake Bay. This project also constructs a park access path enhancement.
The Croydon Creek & Calvin Park Tributary Stream Restoration project (The Project) is located within the Rock Creek Watershed. Rock Creek originates in northern Montgomery County, passes briefly through Rockville, and continues through the District of Columbia to meet the Potomac River. The Rock Creek watershed encompasses four (4) square miles of the eastern side of the City. The watershed includes parts of Rockville Town Center and the Rockville Pike/Hungerford Drive corridors, the neighborhoods of Lincoln Park, East Rockville and Twinbrook, and industrial areas along Gude Drive and Southlawn Lane, as well as Redgate Park and Civic Center Park.
The Project is within a park solely owned by the City of Rockville. This project includes two separate stream segments. Between the segments is a stream section previously restored by the Washington Sanitary Sewer Commission. The Croydon Creek Stream segment begins at a failed dam northwest of the Glenview Mansion and continues easterly to Rock Creek Regional Park. The Calvin Park Tributary segment begins at Baltimore Road and flows in a northerly direction to Croydon Creek. Both stream segments are in poor condition, are highly eroded, over-widened, and are poorly graded. Excessive erosion over time has resulted in sediment accumulation throughout the proposed project area as well as sediment transport downstream.
The Croydon Creek & Calvin Park Stream Restoration project is designed to improve water quality and restore habitat both in stream and within the forested buffer. The proposed design includes natural channel design techniques, such as rock weirs and riffle grade control structures, to provide lifting of the channel to reconnect to the floodplain during storm flows and to enhance in-stream habitat. Additionally, a new pedestrian bridge crossing is included to cross an outfall channel originating at Norbeck Road, along the Heritage Trail. 
Mayor and Council History
The Mayor and Council authorized the City Manager to sign a memorandum of agreement with the U.S. Army Corps of Engineers and the Maryland Historical Trust to allow the City of Rockville to remove a historic dam in Croydon Creek as part of the stream restoration project on November 7, 2022.
Additionally, the Mayor and Council authorized the City Manager to sign a grant agreement with the Maryland Department of Natural Resources (DNR) in the amount of $2,000,000 to partially fund the cost of the stream restoration project on January 9, 2023. 
Public Notification and Engagement
On June 6, 2018, the city and its consultant, AECOM, held the 30 percent design community meeting for the Croydon Creek & Calvin Park Tributary Stream Restoration Project. Topics discussed at the meeting included the expected project goals and outcomes, design alternatives, and the potential impacts to the community. The meeting, held at the Croydon Creek Nature Center, was followed by a stream walk to review the existing conditions of the stream.
On November 12, 2019, the city and its consultants, AECOM, US Army Corps of Engineers (USACE) and the Maryland Historical Trust held a Consulting Party meeting regarding the removal of a Historic Dam in Croydon Creek as part of the scheduled stream restoration project.
The following people/organizations were invited:
• Montgomery County Historic Preservation Division
• City of Rockville Historic Preservation Planner (Historic District Commission representative)
• East Rockville Civic Association
• Montgomery Preservation
• Peerless Rockville
• Montgomery Heritage Area
• Twinbrook Civic Association
• Advisory Council on Historic Preservation
• Tribal Historic Preservation Officer
• Director of Cultural Resources &Section 106, Delaware Nation
• Historic Preservation Officer, Seneca-Cayuga Nation
The following people/organizations attended:
• City of Rockville Project Management Team
• City of Rockville Historic Preservation Planner and Historic District Commission Liaison, Sheila Bashiri
• Ethan Bean, United States Army Corps of Engineers (USACE)
• Beth Cole, Maryland State Historic Preservation Office (MD SHPO, Maryland Historical Trust)
• AECOM/ESA, Project Engineer Consultants
• Lou Kallas, Twinbrook Citizens Association
• Deborah Landau, East Rockville Civic Association
On December 7, 2024, the city and its consultant, AECOM, held a third community meeting at the Croydon Creek Nature Center to present the final design, construction duration and schedule, and community impacts, while listening to community and stakeholder feedback. This input was incorporated into the specifications for the construction contractor.

Procurement
Staff prepared and publicly advertised IFB #25-25 on July 11, 2025, in accordance with Rockville City Code section 17-61. IFB #25-25 was posted on the City website and electronically provided to 766 prospective bidders via the State of Maryland e-Marketplace Advantage (eMMA) system. Of the 766 prospective bidders, using the systems reporting capabilities, 131 were Disadvantaged Business Enterprises (DBE), 136 were Minority Business Enterprises (MBE), and 16 were Veteran-Owned Small Business Enterprises (VSBE).
Sealed bids were received and opened on August 26, 2025, at 2:00PM EST. The following bids were received.
|
Vendor |
MFD-V Status |
Location |
Base Bid |
Contingent Items |
Total Bid Amount |
|
ARRC, LLC |
Non MFD-V |
York, PA |
$4,599,992.25 |
$32,337.50 |
$4,632,329.75* |
|
Meadville Land Service, Inc. |
Non MFD-V |
Cochranton, PA |
$5,599,925.40 |
$19,062.50 |
$5,618,987.90 |
|
Bourn Environmental, LLC |
MFD-V |
Mitchellville, MD |
$4,799,890.00 |
$48,610.00 |
$4,848,500.00 |
|
PayDirt, LLC |
MFD-V |
Edgewater, MD |
$5,791,250.60 |
$12,250.00 |
$5,803,500.60 |
|
Sagres Construction Group |
Non MFD-V |
Alexandria, VA |
$4,926,276.95 |
$14,005.65 |
$4,940,282.60 |
|
EQR, LLC |
Non MFD-V |
Gambrills, MD |
$4,862,252.50 |
$16,140.00 |
$4,878,392.50 |
* $8,650.00 added to Contract in case of a need for additional tree removal to equal $4,640,979.75
Aquatic Resource Restoration Company (ARRC, LLC), is the lowest, responsive and responsible bidder for the Croydon Creek & Calvin Park Tributary Stream Restoration project. The proposed unit prices have been deemed fair and reasonable by staff. Staff found the references for ARRC, LLC and their Subcontractors to be satisfactory for this bid.
Effective October 4, 2025, AARC, LLC has been formally, wholly absorbed into its parent company Kinsley Construction, LLC as part of a strategic consolidation. AARC, LLC included in their bid response that the absorption was currently underway at the time, and has worked with Procurement to update all necessary documents. Staff found the references for Kinsley Construction, LLC and their Subcontractors to be satisfactory for this bid.
The total amount of the contract award includes contingent items for which the city received pricing in the bid but were not included in the tabulation of the sealed bids. The Croydon Creek & Calvin Park Tributary Stream Restoration bid is between 4% - 5% higher than the Engineer’s estimate and allows for contingency dollars within the CIP for the construction of this project, should they be necessary.
In accordance with Section 17-39 of the Rockville City Code, Awarding Authority, (a) all contracts involving more than two hundred fifty thousand dollars ($250,000) shall be awarded by the Mayor and Council.
Both AARC, LLC and Kinsley Construction, LLC are Non-MFD-V businesses.
The contract to Kinsley Construction, LLC is provided as Attachment 1.
To view all contract documents, please click the link provided below:
<https://www.swisstransfer.com/d/bb1386db-bea1-4418-b440-3de70bebc257>

Fiscal Impact
Mayor and Council previously authorized the City Manager to sign a Grant Agreement with DNR for the Croydon Creek/Calvin Tributary Stream Restoration Project (SB16). This grant provides $2,000,000 to the project (SB16).
Funding for this contract is provided within the Stream Restoration Croydon Creek/Calvin Park Tributary (SB16) project (Attachment 2). This CIP designs and constructs stream restoration at Croydon Creek and the Calvin Park Tributary to Rock Creek. Sufficient funding is available in this project for award.

Next Steps
Upon Mayor and Council award, the Procurement Department will obtain insurance certificates, one hundred percent payment and performance bonds, appropriate contract signatures, and issue a contract to Kinsley Construction, LLC, of York, PA.
