Subject
title
Award and Authorize the City Manager to Execute a Design-Build Contract and an Operations and Maintenance Contract Responsive to RFP #22-26, Multi Facility Solar Rooftop and Carport Photovoltaic Systems, to SPH Solutions, LLC in the aggregate amount of $2,387,614 for Solar Photovoltaic Systems at City Hall, 6 Taft Court, and F. Scott Fitzgerald Theatre
end

Department
PW - Environmental Management

Recommendation
Staff recommends that the Mayor and Council authorize the City Manager to:
1. Award and execute a Design-Build contract (Attachment 1) with SPH Solutions, LLC in the amount of $2,325,564, limited to solar photovoltaic systems at City Hall, 6 Taft Court, and F. Scott Fitzgerald Theatre.
2. Award and execute an Operations and Maintenance (O&M) contract (Attachment 2) with SPH Solutions, LLC, in the amount of $62,050, for the same three facilities, for a five year term.

Discussion
Staff is requesting award and authorization of a Design-Build Contract and an O&M Contract responsive to RFP #22-26, Multi Facility Solar Rooftop and Carport Photovoltaic Systems, to SPH Solutions LLC. This project advances several actions identified in Rockville’s Climate Action Plan (CAP, adopted January 10, 2022) and the Rockville 2040 Comprehensive Plan (adopted August 3, 2021):
• Implementing CAP Action M-04, Identify and install feasible solar photovoltaic systems on City property
• Supporting 2040 Comprehensive Plan Environment Action 2.1, Promote and support collective and individual actions by the City, residents, and businesses to reduce greenhouse gas emissions and other air pollutants.
• Implementing 2040 Comprehensive Plan Environment Action 3.1, Implement projects at City facilities to improve energy efficiency, use of renewable energy, and back-up power generation for critical City facilities and services. Work toward meeting or exceeding LEED, ASHRAE, Energy Star, or similar ‘green’ building certification standards.
Background
The City issued a Request for Proposals (RFP) #22-26 to consider and select a qualified and experienced contractor to provide a complete, turn-key design, equipment supply, and installation of Solar PV at seven City facilities: City Hall, 6 Taft Court, F. Scott Fitzgerald Theatre, Swim and Fitness Center, Rothgeb Maintenance Yard, Recreation Services Complex, and the Senior Center.
The solicitation sought proposals that delivered both technical quality and cost efficiency to ensure long-term system reliability and value for the community. The city sought proposals from respondents that have demonstrated experience designing, planning, scheduling, permitting, and constructing complete solar PV systems, have local knowledge of local utilities, provide project financial analysis, and provide system monitoring services.
Capital Purchase or SPPA
RFP #22-26 solicited proposals for both a capital purchase and a Solar Power Purchase Agreement (SPPA), allowing the City to consider direct ownership and third-party ownership options. Under capital purchase, the City purchases and owns the solar photovoltaic systems and is responsible for their ongoing operation and maintenance, either directly or through a separate service contract. Under an SPPA, a third-party provider finances, installs, owns, operates, and maintains the systems on City property, while the City purchases the electricity generated at a contractually established rate over an agreed term. An SPPA generally avoids the upfront capital expense of purchasing the systems but creates a long-term obligation to purchase their electricity, with pricing and any annual escalation established in the agreement.
Recommendation
The recommended awardee, SPH Solutions, LLC, submitted a proposal meeting RFP requirement and had the highest Evaluation Committee Score relative to other evaluated proposal submissions.
Staff recommends a capital purchase because the proposed SPPA rates were not competitive with the City’s existing Pepco utility rates and would increase annual electricity costs rather than provide savings in a sequential construction schedule. The City sought to retain ownership of the Solar Renewable Energy Certificates (SRECs) generated under both direct-ownership and SPPA scenarios. This affects SPPA pricing because third-party system owners can otherwise sell the SRECs and use the proceeds to support lower rates. Retaining and retiring the SRECs allows the City to substantiate claims regarding its use of the associated renewable electricity. In contrast, the recommended capital purchase would provide a total of 590.92 kilowatts of direct-current (DC) solar capacity through a rooftop installation at City Hall and solar carport installations at 6 Taft Court and F. Scott Fitzgerald Theatre, with projected annual electricity savings of approximately $166,663 before operations and maintenance expenses. This results in an aggregate simple payback of 12.65 years after accounting for Maryland Energy Administration (MEA) grant funds.
|
As illustrated in the highlighted blue rows in Table 1, staff recommends limiting the award to these three facilities to advance Building Energy Performance Standards (BEPS) compliance planning at City Hall and 6 Taft Court and align with MEA awarded grant funding at 6 Taft Court and F. Scott Fitzgerald Theatre. The sequential construction scope at these three facilities also minimizes disruption to the public, staff, and City operations, while ensuring efficient construction coordination and project oversight toward completion in calendar year 2028. A separate O&M contract would provide ongoing system support from the system operational date.Table 1: SPH Solutions, LLC RFP Results and Site Considerations |
|
Staff Recommendation |
Facility |
Installation Type |
System Capacity (kW DC) |
MEA Grant |
BEPS Compliance Year |
Capital Purchase Price |
Projected Annual Electricity Savings |
O&M Price (Annual) |
O&M Price (5-Year) |
|
Recommended Award |
City Hall |
Rooftop |
154.98 |
N/A |
Interim 2029 Final 2034 |
$410,787 |
$44,760 |
$3,255 |
$16,275 |
|
|
6 Taft Court |
Carport Canopies |
220 |
$110,000 |
Interim 2029 Final 2034 |
$966,295 |
$63,738 |
$4,620 |
$23,100 |
|
|
F. Scott Fitzgerald Theatre |
Carport Canopies |
215.94 |
$107,970 |
Not applicable |
$948,482 |
$58,165 |
$4,535 |
$22,675 |
|
Total (Recommended Award) |
590.92 |
$217,970 |
|
$2,325,564 |
$166,663 |
$12,410 |
$62,050 |
|
Reserve for Potential Future Solicitation |
Swim and Fitness Center |
Carport Canopies |
340 |
N/A |
Interim 2031 Final 2036 |
$2,094,461 |
$88,278 |
$5,437 |
$27,185 |
|
|
Rothgeb Maintenance Facility |
Rooftop & Carport Canopies |
1,055 |
Transferring to F. Scott Fitzgerald Theatre |
Not applicable |
$5,296,244 |
$272,390 |
$16,880 |
$84,400 |
|
|
Recreation Services |
Rooftop |
97 |
N/A |
Not applicable |
$391,979 |
$26,357 |
$1,556 |
$7,780 |
|
|
Senior Center |
Carport Canopies |
130 |
N/A |
Compliant |
$799,968 |
$34,383 |
$2,077 |
$10,385 |
|
Total (Potential Future) |
1,622 |
|
|
$8,582,652 |
$421,408 |
$25,950 |
$129,750 |
|
TOTAL (All Recommended + Potential Future) |
2,212.92 |
$217,970 |
|
$10,908,216 |
$588,071 |
$38,360 |
$191,800 |
Staff recommends limiting this award to the three identified facilities based on the following considerations:
1. City Hall and 6 Taft Court have been identified by City staff as facilities requiring compliance with Montgomery County BEPS. Prioritizing these locations directs investment toward facilities with an identified regulatory need. The County’s BEPS framework provides credit for qualifying onsite renewable energy, allowing solar generation to support a building’s compliance strategy. Solar installation is being evaluated alongside other necessary energy improvements and does not, by itself, establish BEPS compliance.
2. The carport canopy installations at 6 Taft Court and F. Scott Fitzgerald Theatre align with Maryland Energy Administration FY23 solar canopy grant awards, which support solar generation over parking areas and provide an additional use for existing developed land. The supplied project system capacity estimates identify potential grant rebates of $110,000 and $107,970, respectively. These amounts remain subject to grant amendments and confirmation at project completion under the applicable grant agreements.
3. The scope of the recommended award prioritizes locations and installation types where construction can be coordinated to minimize interference with public access, employee activities, parking, facility programming, and ongoing City services. Rooftop solar was selected for City Hall because the roof offers suitable capacity for installation and favorable electrical routing to the building’s meter. Carport canopies at this location would cause substantial parking lot disruption, adversely affect building occupants, require significant tree removal, and present challenges for zoning, underground utilities, and traffic flow for large emergency vehicles and refuse trucks. Solar carport canopies were selected for 6 Taft Court and the F. Scott Fitzgerald Theatre because the proposed locations offer short electrical connection distances to the building meters and sufficient space for sizable installations with strong projected annual energy production. Construction at these locations is also expected to cause minimal disruption. Rooftop solar at both locations is not viable due to space limitations from rooftop mechanical equipment and shading. Together, the selected sites and installation types support efficient solar deployment while minimizing construction impacts and maintaining continuity of City operations. operations.
4. Limiting the award to these three facilities establishes a focused scope that staff considers achievable within the proposed schedule. It allows the City and contractor to coordinate design, approvals, procurement, construction, and commissioning toward completion in calendar year 2028.
Together, these considerations provide a basis for advancing the three selected facilities without expanding the present award to other locations. This recommendation does not constitute a determination that other facilities are unsuitable for future Solar PV projects.
Potential Future Solar Installations
Solar installations at the remaining four facilities may be considered separately in the future under separate solicitations, subject to further evaluation, funding availability, and applicable approvals. This will also allow additional time to implement other planned facility projects and to apply for MEA grants and align potential grant funding with the installations.
|
Table 2: Potential Future Solar Installations and Considerations |
|
Facility |
Site Considerations |
|
Swim and Fitness Center |
Additional time is needed for design of EV charging stations under an existing National Electric Vehicle Infrastructure (NEVI) grant. Additionally, the extended distance to the building’s electrical meter would require parking lot disturbance and carefully planned construction coordination with the Center’s operations to minimize impacts to operations. |
|
Rothgeb Maintenance Facility |
Installation would need to occur after pending site modifications identified in the Rothgeb Master Plan (CIP GB26) are complete, including fencing, building demolition, grading, and parking lot changes. Staff secured a $103,500 MEA grant in Fiscal Year 2026 to support long-term energy planning at the Rothgeb Maintenance Facility. The planning scope includes battery energy storage, direct current fast charging stations, and solar PV systems. Deferring solar PV installation will allow staff to incorporate planning findings to optimize future integration of these energy systems. |
|
Recreation Services |
Additional time is needed for long-term plans for aging buildings at the complex. A combined material bin cover and solar canopy installation is under consideration for future fiscal years (FY 2030 - FY 2031). Long-range CIP planning identifies building renovations in 2033. |
|
Senior Center |
Installation would need to occur after the pending entrance construction project. The extended distance to the building’s electrical meter would require substantial parking lot disturbance, severely limit parking availability, and cause disruption to building occupants during construction. |

Mayor and Council History
This is the first time this item has been brought before the Mayor and Council.

Boards and Commissions Review
The proposed solar carport canopies project at F. Scott Fitzgerald Theatre has been reviewed and approved by the Maryland Historical Trust. The project has also been reviewed and conditionally approved by the Rockville Historic District Commission at its November 19, 2026, meeting.

Procurement
Staff prepared and publicly advertised RFP #22-26 on April 30, 2026, in accordance with Rockville City Code section #17-62. RFP #22-26 was posted on the City’s website and electronically provided to 145 prospective bidders via the State of Maryland eMaryland Marketplace Advantage (eMMA) system. Of the 145 prospective bidders using the system’s capabilities, 6 were Disadvantaged Business Enterprises (DBE) and 8 were Minority Business Enterprises (MBE).
The evaluation committee consisted of staff from DPW assisted by the Procurement Department. DPW staff ranked the proposals based on four criteria:
|
Evaluation Criteria |
|
Tab Assignment |
Category |
Maximum Points |
|
A |
Firm’s Qualifications and Experience |
25 |
|
B |
Similar Projects/References |
25 |
|
C |
Project Technical Approach and Implementation Schedule |
35 |
|
D |
Price Proposal/Fee Schedule |
15 |
|
|
|
|
|
MAXIMUM TOTAL POINTS |
100 |
Sealed proposals were received on June 25, 2026. Three (3) proposals were received:
|
Contractor |
MFD-V Status |
Location |
Rankings |
|
SPH Solutions Inc. |
MFD-V |
Columbia, MD |
1 |
|
McClure Company |
NON-MFD-V |
Westminster, MD |
2 |
|
Home Discounters |
NON-MFD-V |
Bowie, MD |
3 |
The evaluation committee determined SPH Solutions Inc. to have best met the criteria in the solicitation. The proposer demonstrated strong project experience, sound technical approach, and fair and reasonable pricing consistent with current market rates.
SPH Solutions Inc. was determined to be the highest scoring offeror with the best value.
References were contacted, and all received were favorable of their experiences with SPH Solutions Inc.
SPH Solutions Inc. is a small (MFD-V) business.
There are two (2) contracts, one contract for the design and installation and one contract for the operation and maintenance. The contracts are attached as Attachment 1 and Attachment 2.
To view contract documents, which are not deliberative, potentially proprietary and/or confidential, please click the link provided below:
Non Proprietary and Confidential Contract Documents <https://rockvillemd.legistar.com/View.ashx?M=AO&ID=184795&GUID=8487ba9f-0007-4364-bb8a-a8e352c8bd92&N=QWdlbmRhIDI2LTIzNzhfQ29udHJhY3QgRG9jdW1lbnRz>
Deliberative, potentially proprietary and/or confidential documents may be furnished via a non-public medium to council members if needed. 
Fiscal Impact
This is a multi-year initiative with funding from the CIP for Design-Build and the operating budget for the 5-year O&M agreement.
• Design-Build: Funding for the Design-Build of the Solar PV across the three facilities, amounting to $2,325,564, is available through the Building Efficiency Performance Improvements CIP (Project GA27).
• O&M: Funding for the 5-year O&M agreement, amounting to $62,050 ($12,410 annually), is anticipated to be included as an operating cost impact (OCI) in a future operating budget.
The carport canopies align with FY23 Maryland Energy Administration grant rebates totaling approximately $217,970, calculated at $500 per planned installed kW DC.
The systems would collectively generate approximately $166,663 in annual electricity savings. This results in an aggregate simple payback of 12.65 years for capital costs after accounting for MEA grant funds.
|
Budget |
Solar PV |
|
CIP GA27 |
$2,325,564 (Design-Build) |
|
FY 2028 - FY 2032 Operating |
$62,050 cumulative (5-year O&M agreement, $12,410 annually) |

Next Steps
If approved by the Mayor and Council, the City Manager will execute both the Design-Build contract and the O&M contract with SPH Solutions, LLC.
Staff will coordinate design, permitting, construction, and commissioning while minimizing disruption to the public, staff, and City operations. Operations and maintenance services will begin as specified in the O&M contract.